Fluidr
about   tools   help   Y   Q   a         b   n   l
User / WSDOT / A new merge
Washington State Dept of Transportation / 33,699 items
During the weekend closure, crews on the SR 520 Floating Bridge and Landings Project adjusted the westbound SR 520 merge to allow for a longer and smoother transition from three lanes to two lanes.

Crews on the SR 520 West Approach Bridge North Project poured concrete for intermediate diaphragms to support girders and installed handrail at the westbound SR 520 freeway transit stop. Crews on the SR 520 Floating Bridge and Landings Project completed key remaining items on the new bridge and re-striped the westbound SR 520 merge lane. Crews on the SR 520 Eastside Transit and HOV Project worked on the Evergreen Point, 84th and 92nd Avenue Northeast lids.

Find out more about the new SR 520 on our website.
Popularity
  • Views: 3633
  • Comments: 0
  • Favorites: 0
Dates
  • Taken: Oct 8, 2016
  • Uploaded: Oct 11, 2016
  • Updated: May 24, 2017